Header Ads

Padma Multipurpose Bridge

The Padma Multipurpose Bridge is a multi-purpose road-rail field on the other side of the Padma River, the main tributary of the Ganges in Bangladesh. It connects with Shariatpur and Madaripur, in the south-west, north and east of the country. The field was inaugurated on 25 June 2022.

The Padma Multipurpose Bridge is considered to be the most difficult construction design in the history of Bangladesh. The two-position sword stilt ground carries a four-lane trace in the upper position and a single track road in the lower position. With a span of 150.12 meters (492.5 feet) long, 41 spans, a total length of 6.241 km (3.878 miles) and a range of 22.5 meters (74 feet), it is the longest land in Bangladesh, and in terms of both spans it is the longest and total length above the Ganges. The highest depth of this land mass is 122 meters, which is the highest of all the other islands. The soil of Padma is the deepest soil in the world.

With the launch of the Padma Multipurpose Bridge, Bangladesh's GDP is expected to grow significantly by 1.2 percent.

Coordinates           23.4443°N 90.2610°E

Carries                  Motor vehicles, Railway

Official name        Padma Multipurpose Bridge

Owner                  Bangladesh Bridge Authority

Website               www.padmabridge.gov.bd

Next upstream      Lalon Shah Bridge

Characteristics

Design                          Truss bridge

Total length                   6.241 km (20,470 ft)

Width                             18.18 meters (59.6 feet)

Height                            120 meters (394 feet)

Water depth                    122 m (400 ft)

No. of spans                    41

Load limit                       10,000 tonnes

No. of lanes                     4

History 

Designer                         AECOM

Constructed by               China Major Bridge Engineering Co. Ltd.

Construction start           November 26, 2014

Construction end            23 June 2022[2]

Construction cost           30193.39 crore (US$3.6 billion) (2018 estimates)[3]

Opening                         25 June 2022 09:00 (BST)

Inaugurated                    25 June 2022

Statistics

Toll                                 Yes

History

On 18 September 1998, a design worth the money. Crores of rupees were proposed for the construction of a ground on the Padma River on the Dhaka-Mawa-Bhanga-Khulna Highway for direct communication between the capital and the south and south-west of the country. 5 km long and 18.10 m wide, this field is considered to be the longest possible field in the country. Construction was proposed to begin in July 1999 and will be completed in June 2004. The proposed amount is Rs 1 crore from foreign sources and Rs 750 crore from main sources.

 In the 2006-2007 Annual Development Program, the Government of Bangladesh also adopted a plan to build the Padma Multipurpose Bridge.

 The Bangladesh Bridge Authority (BBA) invited pre-qualification tenders for the design in April 2010. Construction of the ground will begin in early 2011 and will be ready for a major overhaul in 2013 (and all sections will be completed by the end of 2015).

 Following allegations of corruption by some people involved in design drugs, the World Bank withdrew its commitment and other donors followed suit. The Bangladesh government has decided to finance the design itself.

China has proposed to build the ground on a figure-operating-transfer (BOT) basis by investing 2 2 billion or 70 percent of the design cost. Four companies - China Major Bridge Engineering Company, Daily-L&T JV and Samsung C&T Corporation - bought the tender papers. Still, only Chinese companies submitted their financial proposals on April 24, 2014.

On June 17, 2014, significant progress was made in the construction of the Padma Multipurpose Bridge. A construction company, China Bridge Engineering Co., Ltd., was hired to build the long-awaited site at Padma Lock. The 6.15 km site is estimated to bring in Rs 91.72 billion (US 1. 1.1 billion).

Overview of design

The detailed design of the Padma Multipurpose Bridge is being provided by a platoon of international and public advisors led by AECOM. The platoon includes AECOM, SMEC International, Northwest Hydraulic Advisors and ACE Advisors, with new support from Aas-Jakobsen and HR Wallingford.

The design consists of two stages. Phase 1 includes the design phase which leads to the award of construction contracts through procurement activities. Phase 2 is the construction phase. Phase 1 begins on January 29, 2009. A dedicated design office was established in March 2009 in Dhaka. Detailed design of the main ground was done at AECOM's Hong Kong office. All work performed by the Design Platoon was performed within the framework of AECOM's Quality Management System (QMS) which is solely recognized in AS / NZS ISO 9001. QMS is designed to control all design work adopted by the platoon. A design-specific design operation plan was established at the beginning of the design. In March 2009, the Government of Bangladesh requested AECOM to expedite the design to complete construction by the end of 2013. This required the assembling of a new workforce within the design platoon. The Bangladesh Bridge Authority (BBA) has constituted an internationally respected panel of experts comprising five public and five international experts to review the design at regular intervals. Also, an independent checking mastermind, Flint & Neil, was hired to review the design produced by the design criteria, specification and design platoon so that the design meets the design requirements and to take an independent check of the detailed design of the original. Ground and swash training workshops.

An important aspect of the detailed design was the integration of Bangladeshi counterparts into the design platoon, which allowed for the successful training of a significant number of Bangladeshi manpower in all aspects of design and the transfer of the associated technology to a higher position. Large, intricate design.

Components of the project:

1.            Main bridge

2.            River training works (RTW)

3.            Janjira approach road & selected bridge end facilities

4.            Mawa approach road & selected bridge end facilities

5.            Service area - 2

6.            Resettlement

7.            Environment

8.            Land acquisition

9.            CSC (main bridge & RTW)

10.          CSC (approach roads & service area - 2)

11.          Engineering support & safety team (ESST)

Main bridge 6,150 m (20,180 ft):

             Contractor: China Major Bridge Engineering Co. Ltd, China

             Contract period: 4 years + 1 years (defect liability period)

             Contract cost: BDT: 12,133.39 crore

             Date of work order: 26 November 2014

             Date of completion: December 10, 2020

             Physical progress of work: 100%

River training works 14 km (8.7 mi) length:

             Contractor: Sinohydro Corporation Limited, China

             Contract period: 4 years + 1 years (defect liability period)

             Contract cost: BDT: 9,400 crore

             Date of work order: 31 December 2014

             Date of completion: June 30, 2022

             Physical progress of work: 100%

Janjira approach road & selected bridge end facilities 10.50 km (6.52 mi) length:

             Contractor: AML-HCM JV

             Contract period: 3 years + 1 year (defect liability period)

             Contract cost: BDT: 1097.40 crore

             Date of work order: 8 October 2013

             Date of completion: 31 October 2016

             Physical progress of work: 100%

Mawa approach road & selected bridge end facilities 1.50 km (0.93 mi) length:

             Contractor: AML-HCM JV

             Contract period: 2.5 years + 1 year (defect liability period)

             Contract cost: BDT: 193.40 crore

             Date of work order: 27 January 2014

             Date of completion: 31 July 2017

             Physical progress of work: 100%

Service area-2:

             Contractor: Abdul Monem Ltd

             Contract period: 2.5 years + 1 year (defect liability period)

             Contract cost: BDT: 208.71 crore

             Date of work order: 12 January 2014

             Date of completion: 31 July 2017

             Physical progress of work: 100%

Resettlement:

             Total additional grant: BDT: 645.95 crore (up to September 2019)

             Total no. of plots: 2752

             2418 plots handed over to the PAP (up to September 2019)

             Date of work order: 1 June 2009

             Date of completion: 30 June 2020

Environment:

             Total no. of trees planted: 1,69,957

             Date of work order: 1 June 2009

             Date of completion: 30 June 2021

Land acquisition:

             Total land acquisition:

o             Munshiganj: acquired: 329.64 hectares, handed over: 319.92 hectares

o             Madaripur: acquired: 1601.19 hectares, handed over: 553.18 hectares

o             Shariatpur: acquired: 610.96 hectares, handed over: 579.95 hectares

             Date of work order: 1 August 2006

             Date of completion: 31 December 2019

CSC (main bridge & RTW):

             Consultant: Korea Expressway Corporation, South Korea & Associates

             Contract period: 4 years + 1 years (defect liability period)

             Contract cost: BDT: 383.15 crore

             Date of signing contract: 3 November 2014

             Date of completion: 30 November 2019

             Progress of work: 100%

CSC (approach road & service area):

             Consultant: Special Works Organization (SWO-West), Bangladesh Army in association with Bureau of Research, Testing and Consultation of BUET

             Contract period: 3 years + 1 year (defect liability period)

             Contract cost: BDT: 133.49 crore

             Date of work order: 13 October 2013

             Date of completion: 31 October 2018

             Progress of work: 100%

Engineering Support & Safety Team (ESST):

             ESST: Bangladesh Army

             Contract period: 4 years + 1 years (defect liability period)

             Contract cost: BDT: 72.14 crore

             Date of work order: 13 October 2013

             Date of completion: 31 October 2018

             Progress of work: 100%

Construction and development

As of May 2021, more than 95 constructions of the 6.15-km long bi-league Padma Multipurpose Bridge (spans of all major sword frames were set on the pier) have been completed. China Major Bridge Engineering Corporation (MBEC), which was hired for the original ground, is continuing the work. There are a total of 42 pillars on the ground. There are six piles under each one. The span of the sword was placed on the pillar. There are a total of 41 spans on the ground.

Work on the Padma Multipurpose Bridge is astronomically divided into five corridors - main ground, swash training, two connecting roads and construction of structures (service areas). Sinohydro Corporation of China was hired for the swash training workshop and Abdul Monem Limited of Bangladesh was awarded the contract for construction of two connecting roads and structures.

In October 2017, one and a half times after the start of the original construction work, the first span was placed between Pillars 37 and 38, indicating the timely progress of the design.

On November 27, 2020, construction of all 42 pillars was completed.

The final (41st) span of the ground was installed on 10 December 2020 at 1202 PM.

The last road arbor was installed in the span connecting pillars 12 and 13 of Padma Ground at 1012 am on 24 August 2021.

Before Padma Bridge Day Inclusion Form, June 24, 2022

When finished, the field will be the longest field in Bangladesh.

The 415 beacon posts on the Padma Bridge have access to electricity and light up at any time when it starts to get dark.

On 25 June 2022, Bangladesh High Minister Sheikh Hasina officially inaugurated the ground.

Rivalry and rumors

Padma Bridge is a rebuke of corruption

The Padma Multipurpose Bridge has been embroiled in controversy and controversy since the morning. The World Bank said it had "established credible credentials from various sources that point to a high-level corruption conspiracy between Bangladeshi government officials, SNC-Lavalin directors and individuals with the Padma Multipurpose Bridge project." As a result of the controversial corruption, the World Bank originally refused to allow the proposed loan for the construction of the ground and assessed the conditions for the permanence of the loan addresses to the government. Deputation Minister Syed Abul Hossain had to resign after agreeing to one of the conditions, as he was claimed to be involved in corruption. SNC-Lavalin has adopted a negotiated resolution agreement where the company and its cells were barred 10 times from bidding for the World Bank agreement. This is particularly significant because one of the four criteria required before an international sponsor can agree to a negotiating agreement is "whether the accused party has pleaded guilty." Some assumed that SNC Lavalin had done it.

Even then, allegations of corruption were thrown out in a Canadian court as the main reason for an extension shown as line tapping was not well thought out before the suspects. Thus, all evidence collected from the line valve was discarded. Since the case has relied heavily on the certification of the line valve, the decision to execute the death sentence will no longer be pursued.

In 2017, former ICC prosecutor Luis Gabriel Moreno Ocampo came to Dhaka to cover progress on the controversial Padma Multipurpose Bridge corruption settlement. The World Bank has transferred a panel of three led by Ocampo to review the ACC's acquisition process. As per the panel's recommendation, the ACC filed a case accusing former Clerk of the Island Division Mosharraf Hossain Bhuiyan and six other high-ranking government officials. Yet, the same Canadian court acquitted three directors that SNC-Lavalin Group Inc employees planned to buy Bangladeshi officials in ground design, in the same context mentioned earlier.

Rumors are spreading on social media platforms like Facebook that the construction of the Padma Bridge will require a mortal head in July 2019. As a result, many people were beaten in different corridors of Bangladesh and handed over to the police. Subsequently on 9 July 2019, the Ground Construction Authority transferred an announcement to the media that the incident was rumored and unreasonable. Examiners have advised the ground authorities to spread all the details of the field construction among the people.

Operation and facilities

This field will quickly connect Dhaka with Kolkata. At least 2 hours of travel time will be saved. The southern part of Bangladesh will be connected with Dhaka in a short time. If the ground is opened, another Kolkata-Dhaka international train may be launched via Mawa, Goaland, Faridpur, Kushtia, Poradaho, Darshana and Gede.

See also

• 99th Composite Brigade, a Bangladesh Army squad stationed to insure security of the ground

• Ganges Barrage Project, another proposedmega-project to combat the water insufficiency caused by the Farakka Barrage

• Jamuna Bridge, a analogous completed ground across the Jamuna River

• Sheikh Russel Cantonment, a cantonment erected near the Padma Multipurpose Bridge

• List of megaprojects in Bangladesh

• Padma Bridge graft reproach

No comments

Powered by Blogger.